During the last six months, Dave Brodersen and crew have completed much of the feed mill construction—despite a very cold, snowy winter! Even during the trying winter weather, work still progressed, allowing other trades to begin their work this spring.
All of the material handling equipment and processing equipment is in place. Major subcontractors are finishing their work in anticipation of having WEM Automation on site in late May for plant commissioning.
The following subcontractors have joined the Younglove design/build team:
Metal Buildings: Jensen Builders Ltd., Fort Dodge, Iowa
Electrical Contractor: Venteicher Electric, Inc., Coon Rapids, Iowa
Mechanical Contractor: Scheck’s, Inc., Carroll, Iowa
Control Contractor: WEM Automation, Inc., New Berlin, Wisconsin
Process Piping Contractor: Knutson Brothers, Inc., Redwood Falls, Minnesota
Painting Contractor: Merchant Painting, South Sioux City, Nebraska